# The first 90 days after the Cyber Security and Resilience Bill duties start — Cyber Security and Resilience Bill

> Your 90 days start when the relevant duty in the Cyber Security and Resilience Bill (CSRB) comes into force, not on Royal Assent. No start date has been set. This plan counts from day 0 of commencement, with the three-month registration deadline as the main milestone and reporting live from day one.

Canonical page: https://cybersecurityandresiliencebill.com/guides/first-90-days
Updated: 2026-11-09

Status checked 13 November 2026: the Bill passed the House of Lords on 2 November 2026 and returns to the Commons, which is due to consider the Lords amendments on 24 November 2026. On 4 November 2026 the Commons extended its carry-over, so it lapses if not passed by the end of 29 April 2027. It is not yet law. References are to HL Bill 62 (as amended on Report), so wording and numbering may still change in the final Act. This guide is general information, not legal advice.

## Key points

- Count from the commencement date of each duty, set by regulations under clause 69, not from Royal Assent.
- Registration is due within three months; incident reporting applies from the day it starts.
- Register a fortnight early and link director and address changes to the 7-day update duty.
- Rehearse the reportability decision, 24 and 72-hour notices, customer notices and updates before day 0.

## When does the 90-day clock start?

It starts when the relevant duty comes into force, not on Royal Assent. Under clause 69 of HL Bill 62, the Cyber Security and Resilience Bill (CSRB) leaves Part 2, which covers registration, security duties and incident reporting, to [commencement](/glossary/commencement) regulations. These can set different days for different duties.

This plan uses **day 0** to mean the day a given duty starts. The steps and timings are our suggestions, except the ones marked as legal deadlines. The Bill passed the Lords on 2 November 2026 and is not yet law.

## What are the legal deadlines?

Only a few deadlines are fixed in the text. The rest of this plan is about meeting them comfortably.

| Duty | Who | Deadline | Provision |
|---|---|---|---|
| Register with the Information Commission | RMSPs | 3 months from clause 14 starting, or from first meeting the RMSP conditions | Reg 14C |
| Register or update registration | RDSPs | 3 months from clause 14 starting, or from first meeting the conditions | Reg 14 |
| Give Ofcom your details | Data centre OESs | 3 months from being deemed or designated an OES | Reg 8ZA |
| Nominate a UK representative | Overseas RMSPs and RDSPs | 3 months, as above | Regs 14D and 14A |
| Report changes to registration details | RMSPs, RDSPs, data centres | Within 7 days of the change | Regs 14C(5), 14(3), 8ZA(6) |
| Initial incident notification | All regulated persons | Within 24 hours of first awareness | Regs 11, 11A, 12A, 14E |
| Full incident notification | All regulated persons | Within 72 hours of first awareness | As above |

Reporting duties apply from the day they start. There is no 90-day run-in for reporting, unless transitional regulations under clause 69(7) create one.

## What should you do before day 0?

Use the gap between Royal Assent and commencement to settle the decisions that are hardest to rush.

- **Decide your category.** Record your reasoning for [OES, RDSP or RMSP](/guides/oes-vs-rdsp-vs-rmsp), or why you are out of scope. The [scope checker](/scope-checker) is a quick first pass.
- **Read the commencement regulations.** Note the date for each duty.
- **Check the final text.** Clause numbers changed in the Lords and could change again; the Act will have its own section numbers.
- **Name an owner and a deputy.** One senior person should be accountable, with cover for out-of-hours incidents.
- **Update your incident test.** For OESs, RDSPs and RMSPs, a reportable incident must have affected or be affecting the operation or security of your systems, with a significant UK impact; data centres have their own test. There is no mandatory near-miss reporting. See [what counts as a significant incident](/guides/what-is-a-significant-incident).

## Days 0 to 7: make reporting work

If reporting has started, your first week is about being able to report safely.

- **Assume reporting is live.** Check that the 24-hour runbook works and that on-call staff know it.
- **Find the regulator's channel.** Look for the required form and manner of notifications, and save the CSIRT copy address.
- **Check for grace periods.** Do not assume any. Read the transitional provisions.
- **Brief the board.** Confirm the category, duties, deadlines and owner.

## Days 8 to 30: gather registration data

Registration is short but needs the right entity and live contacts.

- **Gather details.** Name, proper address, directors or partners, and contact details with email addresses and telephone numbers.
- **Pick the registering entity.** In a group, register the company that actually provides the service.
- **Nominate a UK representative** if your principal office is outside the UK. See [UK representatives](/guides/uk-representative).
- **Map customers.** You must be able to tell quickly which UK customers an incident is likely to affect, and then keep them updated. See [customer notification](/guides/customer-notification).

## Days 31 to 60: test and fix

The middle month is for testing your processes against realistic incidents.

- **Run a timed exercise.** Include the reportability decision, the 24-hour notice, the [72-hour report](/guides/72-hour-incident-report-template), customer notices and a follow-up customer update.
- **Compare your controls to guidance.** Use your regulator's guidance, and the [Cyber Assessment Framework](/cyber-assessment-framework) if your regulator uses it.
- **Review supplier contracts.** Ask whether suppliers will tell you about incidents quickly enough for your own deadlines.
- **Fix the biggest gaps.** Prioritise detection, containment and privileged access.

## Days 61 to 90: register and embed

The final month is when the registration deadline falls.

- **Register early.** Do not leave it to the last week. A missed registration is a standard-band failure.
- **Set up change tracking.** Link company secretarial changes to the 7-day update duty.
- **Keep your evidence.** Save your scope reasoning, exercises, decisions and board papers.
- **Schedule a review.** Revisit the plan when the code of practice, guidance or charging schemes appear. See the [secondary legislation tracker](/guides/secondary-legislation-tracker).

## A worked example

This is our illustration, not a prediction. Suppose commencement regulations start registration and reporting for RMSPs on the same day, which we call 1 June.

| Date | Milestone |
|---|---|
| Before 1 June | Scope decision recorded; owner and deputy named; runbook updated |
| 1 June | Reporting live. Registration clock starts |
| 8 June | First-week checks complete; board briefed |
| 1 July | Registration details gathered; UK representative nominated if needed |
| 31 July | Timed exercise complete; gaps logged |
| 15 August | Registration submitted, two weeks early |
| 31 August | Legal registration deadline (three months from 1 June) |

If registration and reporting start on different days, run two clocks.

## Who should be involved?

A short list of named people works better than a large committee.

| Role | What they cover |
|---|---|
| Accountable executive | Decisions, budget and board reporting |
| Security lead | Controls, detection and the incident runbook |
| Legal or compliance | Scope reasoning, contracts and the final text |
| Service delivery | Customer lists, tools and who can access what |
| Communications | Customer notices, updates and media handling |

A smaller provider may have one person covering several roles. Even then, name a deputy for reporting, because the 24-hour clock does not wait for someone to return from leave.

## What will it cost to get started?

The Government's impact assessment used a one-off familiarisation cost of about £1,133 per in-scope managed service provider, in 2025 prices, for reading and understanding the rules. That figure excludes the cost of any security improvements. See [what the Bill will cost you](/guides/compliance-costs).

## What penalties apply?

Under HL Bill 62, registration, UK representative and CSIRT-copy failures fall in the standard band: the greater of £10 million and 2% of turnover. Security duty, incident notification and customer notification failures fall in the higher band: the greater of £17 million and 4% of turnover. These are maximums. See [fines and penalties](/fines-and-penalties).

## Sources

- [HL Bill 62, as amended on Report, 26 October 2026](https://bills.parliament.uk/publications/68323/documents/8980), clauses 13 to 16, 21 and 69
- [Government RMSP factsheet](https://www.gov.uk/government/publications/cyber-security-and-resilience-network-and-information-systems-bill-factsheets/relevant-managed-service-providers)
- [Cyber Security and Resilience Bill impact assessment, November 2025](https://assets.publishing.service.gov.uk/media/690cafd3d4c5f31272d3e6b2/cyber_security_and_resilience_bill_impact_assessment.pdf)
- [Lords Report Stage, Hansard, 26 October 2026](https://hansard.parliament.uk/Lords/2026-10-26/debates/B413EFAE-E7D4-4742-986D-092884E0D8D1/CyberSecurityAndResilience(NetworkAndInformationSystems)Bill)

## Frequently asked questions

### When does the 90-day period start?

It starts on the day a duty comes into force under commencement regulations made under clause 69 of HL Bill 62. Royal Assent alone does not start registration or reporting. The regulations can set different days for different duties, so you may have one date for registration and another for incident reporting, and should run separate clocks.

### Is there a grace period for incident reporting?

Not in the Bill's text. Incident reporting applies from the day it comes into force. Clause 69(7) lets the Secretary of State make transitional or saving provision, which could include a grace period, but none has been announced. Plan on the basis that the 24-hour and 72-hour deadlines apply from day one.

### What are the registration deadlines?

RMSPs and RDSPs must register with the Information Commission within three months of clause 14 coming into force, or of first meeting the conditions if later. Data centre operators must give Ofcom similar details within three months of becoming an OES. Changes must be reported within 7 days. Overseas providers must also nominate a UK representative within the same three months.

### Who should own the plan?

Name one accountable senior executive with a deputy, supported by security, legal or compliance, service delivery and communications leads. A smaller provider may combine roles, but should still name a deputy for reporting, because the 24-hour clock runs at weekends and holidays and does not wait for a single person to become available.